If 6 Men Can Do A Piece Of Work In 14 Days, How Many Men Are Needed To Do The Work In 21 Days?
If 6 Men Can Do A Piece Of Work In 14 Days, How Many Men Are Needed To Do The Work In 21 Days?. 6 × 14 days = 84 units. The total work units is the number of individual work.
If 6 men can do a. How many men are needed to do work in 21 days? Web using logic, if it takes 14 days for 6 men to complete the task, then it would take 3 men 28 days.
Web Using Logic, If It Takes 14 Days For 6 Men To Complete The Task, Then It Would Take 3 Men 28 Days.
If 6 men can do a piece of work in 14 days, how many men are needed to do the work in 21 days? The total work units is the number of individual work. Continuing it would take one man84 days (3 x 28) to complete.
Web As The Number Of Days Increases, The Number Of Men Needed Also Would Be Less.
Web answer (1 of 6): If you divide that ratio. 6 × 14 days = 84 units.
Web Interview Question For Entry Level It Systems Engineer.if 6 Men Can Do A Piece Of Work In 14 Days, How Many Men Are Needed To Do The Work In 21 Days?.
Web up to $15 cash back if 6 men can do a piece of work in 14 days, how many men are needed to do the work in 21 days? Asked • 12/28/17 if 6 men can do a piece of work in 14 days. If 6 men can do a.
Let The Number Of Men Required To Finish.
How many men are needed to do work in 21 days? Let the work done by 6 men be. If 6 men can do a piece of work in 14 days, how many men are needed to do the work in 21 days?
Post a Comment for "If 6 Men Can Do A Piece Of Work In 14 Days, How Many Men Are Needed To Do The Work In 21 Days?"